The GSI Rules commenced on 29 June 2013. All rule changes since this commencement date are outlined in the tables below. These include past proposals considered by the Rule Change Panel (3 April 2017 - 1 July 2021) and the Independent Market Operator (prior to 3 April 2017) under previous governance arrangements.
Links to gazettal notices are also provided for Amending Rules made by the Minister for Energy under regulation 7(5) and 7(6) of the Gas Services Information Regulations 2012.
For more information on proposing a rule change, visit the Rule Change Process webpage.
Amending Rules Gazetted by the Minister since 2015
Gazette | Gazettal Date | Name | Commencement date(s) |
---|---|---|---|
Gazette2021/212 | Gazettal Date17/12/2021 | NameGas Services Information Amendment (AEMO Allowable Revenue) Rules 2021 | Commencement date(s)17/12/2021 |
Gazette2021/183 | Gazettal Date29/10/2021 | NameGas Services Information Amendment (Transitional Provisions) Rules 2021 | Commencement date(s)30/10/2021 |
Gazette2021/17 | Gazettal Date22/01/2021 | NameGas Services Information Amendment (Governance) Rules 2021 | Commencement date(s)01/07/2021 |
Gazette2018/60 | Gazettal Date27/04/2018 | NameGas Services Information Rules Amending Rules 2018 | Commencement date(s)28/04/2018 |
Gazette2016/209 | Gazettal Date25/11/2016 | NameGas Services Information Rules Amending Rules 2016 (No. 2) | Commencement date(s)26/11/2016 |
Gazette2016/116 | Gazettal Date30/06/2016 | NameGas Services Information Rules Amending Rules 2016 | Commencement date(s)01/07/2016 |
Gazette2015/179 | Gazettal Date27/11/2015 | NameGas Services Information Rules Amending Rules 2015 | Commencement date(s)30/11/2015 |
Rejected
ID | Date submitted | Title | Submitted by | Date rejected |
---|---|---|---|---|
GRC_2024_01 | 28/08/2024 | AEMO’s Allowable Revenue Framework | AEMO | 26/02/2025 The Final Rule Change Report included Amending Rules which were approved by the Minister on 17 April 2025. The Amending Rules commenced on 23 April 2025 |
Commenced
ID | Date submitted | Title | Submitted by | Date commenced |
---|---|---|---|---|
IDGRC_2022_01 | Date submitted29/03/2022 | TitlePublication of Tanker Gas Information on the Gas Bulletin Board (GBB) | Submitted byAEMO | Date commenced1/12/2022 |
IDGRC_2018_01 | Date submitted06/07/2018 | TitleGBB Zones | Submitted byAEMO | Date commenced01/03/2019 |
IDNotice of Corrigenda | Date submitted24/04/2018 | TitleNotice of Corrigenda – Market Rules and GSI Rules – 2018_04_24 | Submitted byRule Change Panel | Date commenced24/04/2018 |
IDGRC_2017_01 | Date submitted23/11/2017 | TitleAmendments to Schedule 2 - GBB Zones | Submitted byAEMO | Date commenced03/01/2018 |
IDGRC_2015_01 | Date submitted27/02/2015 | TitleAmendments to Schedule 2 - GBB Zones | Submitted byIndependent Market Operator | Date commenced20/03/2015 |
IDGRC_2014_02 | Date submitted24/02/2014 | TitleSubmission of Medium-Term Capacity Outlook | Submitted byIndependent Market Operator | Date commenced31/07/2014 |
IDGRC_2014_01 | Date submitted09/07/2014 | TitleGSI Fee Arrangements - Inclusion of Registered Production Facility Operators | Submitted byPublic Utilities Office | Date commenced01/01/2015 |