Rule Change: GRC_2014_02

Rule Change Proposal made by the IMO on 24 February 2014
Last updated:

Type: Standard Rule Change Proposal

Submitter: IMO

Title: Submission of Medium Term Capacity Outlook

GSI Rules Affected: Subrules 56(1), 64(1), 71(1) and 130(2)

Date Submitted: 24 February 2014

Current Status: The Amending Rules commenced on 31 July 2014.

Event Date Comments
Notification Published 24/02/2014  
First Submission Period 25/02/2014 - 08/04/2014 The submission period is 30 B-Days from the date the IMO published the Rule Change Notice. During this period no submissions were received.
Draft Report Published 17/04/2014 Must be published within 20 B-Days of the end of the first submission period. The IMO published the Draft Rule Change Report early and has therefore brought forward the subsequent steps in accordance.
Second Submission Period 18/04/2014 - 20/05/2014 The submission period is at least 20 B-Days from the date the IMO published the Draft Report. During this period no submissions were received.
Final Report Published 18/06/2014 Must be published within 20 B-Days after the end of the second submission period.
Ministerial Approval By 16/07/2014 The Minister approved the Final Rule Change Report on 26 June 2014.
Commencement 31/07/2014