Type: Fast Track Rule Change Process
Submitter: Alinta Energy
Title: Estimates for GIA facilities
Market Rules Affected: Clause 7.7.5A and Appendix 9.
Date Submitted: 13 May 2020
Current Status: The Amending Rules commenced at 8:00 AM on 24 June 2020.
Event | Date | Comments |
---|---|---|
Notification Published | 25/05/2020 | Alinta Energy responded to a request for clarification under clause 2.5.5 on 14/05/2020. |
Requests to be Consulted | 25/05/2020 - 02/06/2020 | The last date a Rule Participant can contact the Rule Change Panel requesting to be consulted on the change |
Consultation Period | 25/05/2020 - 09/06/2020 | Must be completed within 15 B-Days from the publication of the Rule Change Notice |
Final Rule Change Report | 23/06/2020 | The Final Rule Change Report must be published within 20 B-Days after the Rule Change Notice is published |
Commencement | 24/06/2020 |