Type: Standard Rule Change Process
Submitter: Public Utilities Office
Title: Full Runway Allocation of Spinning Reserve Costs
Market Rules Affected: Appendix 2
Date Submitted: 26 November 2018
Current Status: The Amending Rules commenced on 1 September 2019.
Event | Date | Comments |
---|---|---|
Notification Published | 29/11/2018 | |
First Submission Period | 29/11/2018 – 30/01/2019 | The submission period is at least 30 B-Days from the publication of the Rule Change Notice. |
Draft Rule Change Report Published | 27/02/2019 | The Draft Rule Change Report must be published within 20 B-Days after the end of the first submission period. |
Second Submission Period | 27/02/2019 – 28/03/2019 | The submission period is at least 20 B-Days from the publication of the Draft Report. |
Final Rule Change Report Published | 30/04/2019 | The Final Rule Change Report must be published within 20 B-Days after the end of the second submission period. |
Commencement | 01/09/2019 |