Type: Fast Track Rule Change Process
Submitter: Rule Change Panel
Title: New Notional Wholesale Meter Manifest Error
Market Rules Affected: Appendix 5
Date Submitted: 24 April 2018
Current Status: The Amending Rules commenced at 8:00 AM on 1 September 2018.
Event | Date | Comments |
---|---|---|
Notification Published | 24/04/2018 | |
Requests to be Consulted | 02/05/2018 | The last date a Rule Participant can contact the Rule Change Panel requesting to be consulted on the change. |
Consultation Period | 24/04/2018 - 11/05/2018 | Must be completed within 15 B-Days from the publication of the Rule Change Notice. |
Final Rule Change Report | 21/05/2018 | The Final Rule Change Report must be published within 20 B-Days after the Rule Change Notice is published. |
Commencement | 01/09/2018 |