Type: Standard Rule Change Process
Submitter: Perth Energy
Title: Implementation of 30-Minute Balancing Gate Closure
Market Rules Affected: Clauses 7A.1.16, 7A.1.17, 7A.2.6, 7A.2.9(d), 7A.2.9(e), 7A.2.12, 7A.3.5, 7A.2A.4(b)(i)(2), 7B.2.4 and the Glossary.
Date Submitted: 4 April 2017
Current Status: The Amending Rules commenced at 8:00 AM on 1 December 2020.
Event | Date | Comments |
---|---|---|
Notification Published | 12/04/2017 | |
First Submission Period | 12/04/2017 - 12/06/2017 | The submission period has been extended in accordance with the Extension Notice published on 22 May 2017. |
Draft Rule Change Report Published | 18/05/2020 | The timeframe for publishing the Draft Rule Change Report was extended in accordance with the Extension Notice published on 28 April 2020. |
Second Submission Period | 18/05/2020 – 23/06/2020 | The timeframe for the submission period was extended in accordance with the Extension Notice published on 3 June 2020. |
Final Rule Change Report Published | 21/07/2020 | The Final Rule Change Report must be published within 20 B-Days after the end of the second submission period. |
Commencement | 01/12/2020 |