Type: Standard Rule Change Proposal
Submitter: IMO
Title: Specific Transition Provisions for the 2015 Reserve Capacity Cycle
Market Rules Affected: Clauses 1.13.1 (new) and 1.13.2 (new)
Date Submitted: 30 March 2015
Current Status: The Amending Rules commenced on 1 September 2015.
Event | Date | Comments |
---|---|---|
Notification Published | 30/03/2015 | |
First Submission Period | 31/03/2015 - 14/05/2015 | The submission period is at least 30 B-Days from the date the IMO published the Rule Change Notice. |
Draft Report Published | 12/06/2015 | Must be published within 20 B-Days of the end of the first submission period. |
Second Submission Period | 15/06/2015 - 10/07/2015 | The submission period is at least 20 B-Days from the date the IMO published the Draft Rule Change Report. No submissions were received. |
Final Report Published | 07/08/2015 | Must be published within 20 B-Days after the end of the second submission period. |
Commencement | 01/09/2015 |