Rule Change: RC_2015_05

A Rule Change Proposal made by the Independent Market Operator on 30 March 2015.
Last updated:

Type: Standard Rule Change Proposal

Submitter: IMO

Title: Specific Transition Provisions for the 2015 Reserve Capacity Cycle

Market Rules Affected: Clauses 1.13.1 (new) and 1.13.2 (new)

Date Submitted: 30 March 2015

Current Status: The Amending Rules commenced on 1 September 2015. 

Event  Date Comments
Notification Published 30/03/2015  
First Submission Period 31/03/2015 - 14/05/2015 The submission period is at least 30 B-Days from the date the IMO published the Rule Change Notice.
Draft Report Published 12/06/2015 Must be published within 20 B-Days of the end of the first submission period.
Second Submission Period 15/06/2015 - 10/07/2015 The submission period is at least 20 B-Days from the date the IMO published the Draft Rule Change Report. No submissions were received.
Final Report Published 07/08/2015 Must be published within 20 B-Days after the end of the second submission period.
Commencement 01/09/2015  

 

Was this page useful?