Rule Change: RC_2014_06

A Rule Change Proposal made by the Independent Market Operator on 28 January 2015
Last updated:

Type: Standard Rule Change Proposal

Submitter: IMO

Title: Removal of Resource Plans and Dispatchable Loads

Market Rules Affected: 2.13.9, 2.16.2, 2.16.4, 2.16.12, 2.22A.1, 2.26.3, 2.27.1, 2.27.5, 2.27.15, 2.29.1A, 2.29.5, 2.29.8, 2.29.8A, 2.30B.2, 2.30B.13, 2.34.3, 2.34.8, 2.34.14, 2.35.1, 2.36.1, 2.37.5, 3.9.2, 3.9.6, 3.13.2, 3.13.3A, 3.13.3AB, 4.1.26, 4.10.1, 4.11.4, 4.12.1, 4.12.4, 4.18.1, 4.18.2, 4.25.2, 4.25.4, 4.26.2, 4.26.2B, 4.26.5, 6.3A.2, 6.3A.4, 6.3B.1, 6.4.1, 6.4.2, 6.4.3, 6.4.4, 6.4.5, 6.4.6, 6.4.6A (new), 6.4.6B (new), entire section 6.5, 6.5A, 6.5B, entire section 6.5C, 6.6.9, entire section 6.11, 6.11A.1, 6.12.1, 6.13, 6.15.1, 6.15.2, 6.16A.1, 6.16A.2, 6.16B.1, 6.16B.2, 6.17.1, 6.17.3, 6.17.4, 6.17.5, 6.17.5A, 6.17.6, 6.17.6A, 6.17.6C, 6.17.7, 6.17.9, 6.21.2, 7.1.1, 7.2.2, entire section 7.4, entire section 7.5, 7.6.1C, 7.6.2B, 7.6A, 7.6A.1, 7.6A.2, 7.6A.3,  7.6A.5, 7.7.4A, 7.7.5, 7.9.4, 7.9.8, 7.11.5, 7.13.1, 7A.1.3, 7A.1.6, 7A.2.1, 7A.2.3, 7A.2.4, 7A.2.4A (new), 7A.2.4B (new), 7A.2.4C (new), 7A.2.8, 7A.2.9, 7A.2.9A (new), 7A.2.10, 7A.2.12, 7A.2.13, most of section 7A.3, 7B.1.4, 7B.1.5, 7B.2.1, 7B.2.2, 7B.2.3, 7B.2.4, 7B.2.5, 7B.2.6, 7B.2.10, 7B.2.18, 7B.2.19, most of section 7B.3, 7B.4, 7B.4.1, 9.3.3, 9.3.4, 9.3.7, 9.8.1, 9.9.2, 9.11.1, 9.13.1, 9.18.3, 9.24.2, 10.5.1, 10.7.1, Chapter 11 (Glossary), Appendix 1, and  Appendix 9

Date Submitted: 28 January 2015

Current Status: The Amending Rules commenced at 8:00 AM on 1 July 2019.

Event Date Comments
Notification Published 28/01/2015  
First Submission Period 29/01/2015 - 02/04/2015 The submission period has been extended to 45 B-Days from the date the IMO published the Rule Change Notice.
Further Submission Period 22/01/2018 - 13/02/2018 A call for further submissions was published on 22 January 2018.
Draft Report Published 31/08/2018 The timeframe for publishing the Draft Rule Change Report was further extended in accordance with the Extension Notice published on 21 December 2017.
Second Submission Period 31/08/2018 – 01/10/2018 The submission period is at least 20 B-Days from the date the Rule Change Panel published the Draft Rule Change Report.
Final Report Published 29/10/2018 Must be published within 20 B-Days after the end of the second submission period.
Ministerial Approval 26/11/2018  
Commencement 01/07/2019  

 