Rule Change: RC_2013_18

A Rule Change Proposal made by Simon Middleton, for the Merger Implementation Group on 11 November 2013.
Last updated:

Type: Fast Track Rule Change Proposal

Submitter: Simon Middleton, for the Merger Implementation Group

Title: Market Rule changes arising due to the merger of the Electricity Retail Corporation and Electricity Generation Corporation

Market Rules Affected: Clauses 1.10.2, 1.10.3, 1.11 (new), 2.2.2, 2.3.5, 2.16.7, 3.11.7A, 3.11.8, 3.13.3A, 3.13.3AB, 4.12.1, 4.14.4, 4.14.5, 4.23A.2, 4.26.2, 6.5.1, 6.5.1A, 6.5.4, 6.5C.1, 6.11.1, 6.11.3, 6.12.1, 6.15.1, 6.15.2, 6.16B.1, 6.16B.2, 6.17.1, 6.17.5, 6.17.5A, 6.17.5B, 6.17.9, 6.17.10, 6.21.2, 7.5.4, 7.6.2, 7.6.2A, 7.6.12, 7.6A.1, 7.6A.2, 7.6A.3, 7.6A.4, 7.6A.5, 7.6A.6, 7.6A.7, 7.6A.8, 7.7.1, 7.10.7, 7.11.5, 7.12.1, 7.13.1, 7.13.1A, 7.13.1C, 7A.1.14, 7A.2.1, 7A.2.2, 7A.2.3, 7A.2.9, 7A.2.10, 7A.2.12, 7A.3.1, 7A.3.5, 7A.4.1, 7A.4.2, 7A.4.4, 7A.4.5, 7A.4.6, 7A.4.8, 7A.4.9, 7B.2.1, 7B.2.2, 7B.2.3, 7B.2.4, 7B.2.5, 7B.2.6, 7B.3.7, 7B.4.1, 7B.4.2, 9.8.1, 9.9.1, 9.9.2, 9.18.3, 10.5.1 and 10.8.2, the Glossary and Appendices 1, 2 and 9

Date Submitted: 11 November 2013

Current Status:  The Minister approved the Amending Rules on 23 December 2013. The transitional Amending Rules commenced on 30 December 2013. The remaining Amending Rules commenced on 1 January 2014

Event Date Comments
Notification Published 11/11/2013  
Requests to be Consulted 18/11/2013 The last date a Rule Participant can contact the IMO requesting to be consulted on the rule change.
Consultation Period 12/11/2013 - 02/12/2013 Must be completed within 15 B-Days from the date the notification is published.
Final Report Published 19/12/2013 The timeframe for preparing the Final Rule Change Report has been extended in accordance with the Extension Notice published on 9 December 2013. 
Ministerial Approval By 27/12/2013 The Minister approved the Final Rule Change Report on 23 December 2013.
Commencement 30/12/2013 and
01/01/2014
 

 

Was this page useful?