Type: Fast Track Rule Change Process
Submitter: IMO
Title: Alignment of Settlement Tolerances and Tolerance Ranges
Market Rules Affected: Clauses 2.13.6L (new) and 6.17.9
Date Submitted: 16 November 2012
Current Status: The Amending Rules commenced on 1 November 2013
Event | Date | Comments |
---|---|---|
Notification Published | 16/11/2012 | |
Requests to be Consulted | 23/11/2012 | The last date a Rule Participant can contact the IMO requesting to be consulted on the change. |
Consultation Period | 19/11/2012 - 07/12/2012 | Must be completed within 15 B-Days from the date the notification is published. |
Final Rule Change Report | 14/12/2012 | Must be published within 20 B-Days from the date the notification is published. |
Ministerial Approval by | 18/09/2013 | The Final Rule Change Report was approved by the Minister on 17 September 2013. |
Commencement | 01/11/2013 |