Rule Change: RC_2012_08

A Rule Change Proposal made by the Independent Market Operator on 1 June 2012.
Last updated:

Type: Fast Track Rule Change Proposal

Submitter: IMO

Title: Constrained On and Off Prices for Non-Scheduled Generators

Market Rules Affected: Clauses 6.17.3A and 6.17.4A

Date Submitted: 01 June 2012

Current Status: The Amending Rules commenced on 1 July 2012

Event Date Comments
Notification Published 01/06/2012  
Requests to be Consulted 11/06/2012 The last date a Rule Participant can contact the IMO requesting to be consulted on the change.
Consultation Period 02/06/2012 - 18/06/2012 Must be completed within 15 B-Days from the date the notification is published
Final Report Published 25/06/2012 Must be published within 20 B-Days from the date the notification is published
Commencement Balancing Market Commencement Day  

 