Type: Standard Rule Change Process
Submitter: Independent Market Operator (IMO)
Title: Prudential Requirements
Market Rules Affected: Clauses 2.37.4, 2.37.9, 2.40.1, new clauses 2.40.1A, 2.40.2, 2.41.2, 2.41.3, 2.42.1, 2.42.2, 2.42.3, 2.42.7, 2.43.1, 10.7.1, and the Glossary
Date Submitted: 15 May 2012
Current status: Closed
Event | Date | Comments |
---|---|---|
Notification Published | 15/05/2012 | |
First Submission Period | 16/05/2012 - 24/08/2012 | The timeframe for the first submission period was extended in accordance with the Extension Notice published on 19 June 2012 |
Draft Report Published | 21/09/2012 | Must be published within 20 B-Days of the end of the first submission period |
Second Submission Published | 24/09/2012 - 22/10/2012 | The submission period is at least 20 B-Days from the date the IMO published the Draft Report |
Final Report Published | 19/11/2012 | The Final Rule Change Report was approved by the Board out of session on 15 November 2012 |
Commencement | Not applicable | The Rule Change Proposal was rejected by the IMO |