Type: Standard Rule Change Process
Submitter: Griffin Energy
Title: Calculation of the Capacity Value of Intermittent Generation – Methodology 2 (Griffin Energy)
Market Rules Affected: Clauses 4.11.3A, 7.7.5B, 7.7.5C, 7.7.5E, 7.13.1,10.5.1 and the Glossary
Date Submitted: 30 November 2010
Current Status: Closed.
Event | Date | Comments |
---|---|---|
Notification Published | 06/12/2010 | |
First Submission Period | 07/12/2010 - 04/02/2011 | The timeframe for the first submission period was extended in accordance with the Extension Notice published on 6 December 2010 |
Draft Report Published | 18/08/2011 | The timeframe for preparing the Draft Report was further extended in accordance with the Extension Notice published on 27 July 2011 |
Second Submission Published | 19/08/2011 - 21/10/2011 | The timeframe for the second submission period was further extended in accordance with the Extension Notice published on 13 October 2011 |
Public workshop | 08/09/2011 | The IMO held a public workshop during the second submission period to present the analysis and recommendations of the Sapere report |
Further Consultation Period | 21/11/2011 - 30/11/2011 | The IMO is providing interested parties with a further consultation period in accordance with the Extension Notice published on 21 November 2011 |
Final Report Published | 20/12/2011 | The Final Report was published after Board approval was given in session on 15 December 2011 |
Commencement | Not Applicable | This rule change was rejected by the IMO |