Type: Standard Rule Change Proposal
Submitter: IMO
Title: Capacity Credit Cancellation
Market Rules Affected: Clauses 2.17.1, 4.12.6, 4.25.12, 4.27.10, 4.27.10A and new clauses 4.1.21A, 4.20.8, 4.20.9, 4.20.10, 4.20.11, 4.20.12, 4.20.13, 4.20.14
Date Submitted: 01 March 2011
Current Status: The Amending Rules commenced on 1 July 2012
Event | Date | Comments |
---|---|---|
Notification Published | 01/03/2011 | |
First Submission Period | 01/03/2011 - 13/04/2011 | The submission period is 30 B-Days from the date the IMO published the Rule Change Notice |
Draft Report Published | 14/12/2011 | The timeframe for preparing the Draft Report was further extended in accordance with the Extension Notice published on 16 November 2011 |
Second Submission Period | 15/12/2011 - 13/02/2012 | The timeframe for the second submission period has been extended in accordance with the Extension Notice published on 16 November 2011 |
Final Report Published | 13/03/2012 | Must be published within 20 B-Days after the end of the second submission period |
Ministerial Approval by | 13/04/2012 | The Minister approved the Amending Rules on 13 April 2012 |
Commencement | 01/07/2012 | The IMO has rescheduled the commencement date to 1 July 2012 (originally 1 August 2012) in accordance with the Public Notice published on 25 June 2012 |