A Rule Change Proposal made by the Independent Market Operator on 18 November 2010.
Last updated:

Type: Standard Rule Change Process

Submitter: IMO

Title: Partial Commissioning of Intermittent Generators

Market Rules Affected: Clause 4.26.1

Date Submitted: 18 November 2010

Current Status: The Amending Rules commenced at 8.00am on 1 October 2011

Event Date Comments
Notification Published 22/11/2010  
First Submission Period 23/11/2010 - 20/01/2011 The timeframe for the first submission period was extended in accordance with the Extension Notice published on 22 November 2010
Draft Report Published 18/03/2011 The timeframe for preparing the Draft Report was extended in accordance with the Extension Notice published on 4 March 2011
Second Submission Period 21/03/2011 - 15/04/2011 The submission period is at least  20 B-Days from the date the IMO published the Draft Report
Final Report Published 22/07/2011 The period for preparing the Final Rule Change Report has been extended until 22 July 2011 in accordance with the Extension Notice published on 16 May 2011
Commencement 01/10/2011  

 