Type: Standard Rule Change Process
Submitter: IMO
Title: Removal of Network Control Services Expression of Interest and Tender Process from the Market Rules
Market Rules Affected: Clauses 2.1.2, 2.8.13, 2.17.1, 2.22.1, 2.37.6, 2.37.7, 2.37.8, 2.38.1, 2.38.2, 2.38.3, 2.38.4, 2.38.5, 5.1.1, 5.1.2, 5.1.3, 5.1.4, 5.2.1, 5.2.2, 5.2.3, 5.2.4, 5.2.5, 5.2.6, 5.2.7, 5.3.1, 5.3.2, 5.3.3, 5.3.4, 5.3.5, 5.3.6, 5.3.7, 5.3.8, 5.3.9, 5.4, 5.4.1, 5.4.2, 5.4.3, 5.4.4, 5.4.5, 5.4.6, 5.4.7, 5.4.8, 5.4.9, 5.4.10, 5.4.11, 5.4.12, 5.4.13, 5.4.14, 5.5, 5.5.1, 5.5.2, 5.5.3, 5.5.4, 5.6, 5.6.1, 5.6.2, 5.6.3, 5.7.1, 5.7.2, 5.8, 5.8.1, 5.8.2, 5.8.3, 5.8.4, 5.8.5, 5.8.6, 5.8.7, 5.8.8, 5.9.1, 6.17.6, 7.1.1, 7.6.6, 7.13.1, 9.12, 9.12.1, 9.12.2, 9.14.1, 9.14.2, 9.18.3, 9.24.3A, the Glossary and Appendix 1 with the addition of new clauses 5.2A.1, 5.2A.2, 5.3A, 5.3A.1, 5.3A.2, 5.3A.3, 5.3A.4, 5.9.2, 5.9.3, 7.6.1A and 10.5.1(vD)
Date Submitted: 15 October 2010
Current Status: The Amending Rules commenced on 1 July 2011
Event | Date | Comments |
---|---|---|
Notification Published | 18/10/2010 | |
First Submission Period | 19/10/10 - 29/11/2010 | The submission period is 30 B-Days from the date the IMO published the Draft Report |
Draft Report Published | 24/12/2010 | Must be published within 20 B-Days of the end of the first submission period |
Second Submission Period | 29/12/2010 - 10/02/2011 | The submission period is at least 20 B-Days from the date the IMO published the Draft Report |
Final Report Published | 11/03/2010 | Must be published within 20 B-Days after the end of the second submission period |
Ministerial Approval | 08/04/2011 | The Minister approved the Final Report on 6 April 2011 |
Commencement | 01/07/2011 |