Rule Change: RC_2009_35

A Rule Change Proposal made by the Independent Market Operator on 21 December 2009
Last updated:

Type: Standard Rule Change Process

Submitter: IMO

Title: Energy Price Limits Methodology and Consultation Process

Market Rules Affected: 6.20.2, 6.20.7, 6.20.9, 6.20.10 and new clause 6.20.9A

Date Submitted: 21 December 2009

Date First Published on the IMO Website: 21 December 2009

Current Status: The Amending Rules commenced on 1 June 2010

Event Date Comments
Notification Published 21/12/2009  
First Submission Period 22/12/2009 - 05/02/2010 The submission period is 30 B-Days from the date the IMO published the notification
Draft Report Published 08/03/2010 Must be published within 20 B-Days after the end of the submission period
Second Submission Period 09/03/2010 - 07/04/2010 The submission period is at least  20 B-Days from the date the IMO published the Draft Report
Final Report Published 06/05/2010 Must be published within 20 B-Days after the end of the second submission period
Commencement 01/06/2010  

 

Was this page useful?