Type: Standard Rule Change Process
Submitter: Economic Regulation Authority
Title: System Management Review Period Budget Coverage Amendment
Market Rules Affected: 2.23.1, 2.23.2, 2.23.3, 2.23.5, 2.23.7, 2.23.12, 3.11.11, 3.11.14, 3.13.1, 3.13.3, 3.13.3A (new), 3.13.3B (new), 3.13.3C (new) and 3.22.1
Date Submitted: 15 July 2009
Date First Published on the IMO Website: 15 July 2009
Current Status: The amending rules commenced at 8:00am 30 November 2009
Event | Date | Comments |
---|---|---|
Notification Published | 15/07/2009 | |
First Submission period | 16/07/2009 – 26/08/2009 | The submission period is 6 weeks from the date the IMO published the notification |
Draft Report published | 10/09/2009 | Must be published within 20 B-Days after the end of the submission period |
Second submission period | 11/09/2009 – 09/10/2009 | The submission period is at least 20 B-Days from the date the IMO published the Draft Report |
Final Report Published | 30/10/2009 | Must be published within 20 B-Days after the end of the second submission period |
Minister's Approval | 27/11/2009 | Clause 2.23 is a protected provision and any amendments require approval by the Minister |
Rule Commencement | 30/11/2009 |