Type: Standard Rule Change Process
Submitter: System Management
Title: The use of tolerance levels by System Management
Market Rules Affected: 2.13.6, 2.13.8, 7.10.5, Chapter 11, 2.13.6A, 2.13.6B, 2.13.6C, 2.13.6D, 2.13.6E, 2.13.6F, 2.13.6G, 2.13.6H, 2.10.5B, 7.10.5B, and 7.10.5C
Date Submitted: 15 October 2009
Date First Published on the IMO Website: 16 October 2009
Current Status: The Amending Rules commenced at 8:00am 1 December 2010
Event | Date | Comments |
---|---|---|
Notification Published | 16/10/2009 | |
First Submission Period | 19/10/2009 - 27/11/2009 | |
Draft Report Published | 09/04/2010 | The timeframe for preparing the Draft Rule Change Report was extended in accordance with the notice of extension published 15 February 2010 |
Second Submission Period | 12/04/2010 - 20/05/2010 | The submission period is at least 20 B-Days from the date the IMO published the Draft Report |
Final Report Published | 18/06/2010 | Must be published within 20 B-Days after the end of the second submission period |
Ministerial Approval | 16/07/2010 | |
Commencement | 01/12/2010 |