Type: Standard Rule Change Process
Submitter: System Management
Title: Timing flexibility for transfer of information from System Management
Market Rules Affected: Clauses 7.2.3C and 7.3.6
Date Submitted: 12 March 2009
Date First Published on the IMO Website: 19 March 2009
Current Status: The amending rules commenced at 8.00am 1 August 2009
Event | Date | Comments |
---|---|---|
Notification Published | 19/03/2009 | |
First Submission period | 19/03/2009 – 30/04/2009 | The submission period is 6 weeks from the date the IMO published the notification |
Draft Report published | 25/05/2009 | Must be published within 20 B-Days after the end of the submission period |
Second submission period | 26/05/2009 – 22/06/2009 | The submission period is 20 B-Days from the date the IMO published the Draft Report |
Final Report Published | 17/07/2009 | Must be published within 20 B-Days after the end of the second submission period |
Rule Commencement | 01/08/2009 |