Type: Standard Rule Change Process
Submitter: System Management
Title: Confidentiality of Accepted Outages
Market Rules Affected: Clause 3.18.5D (New)
Date Submitted: 17 March 2009
Date First Published on the IMO Website: 19 March 2009
Current Status: The amending rules commenced at 8.00am 17 August 2009
Event | Date | Comments |
---|---|---|
Notification Published | 19/03/2009 | |
First Submission period | 19/03/2009 – 30/04/2009 | The submission period is 6 weeks from the date the IMO published the notification |
Draft Report published | 19/06/2009 | This period was extended in accordance with the notice of extension published 22 May 2009. |
Second submission period | 22/06/2009 – 17/07/2009 | The submission period is 20 B-Days from the date the IMO published the Draft Report |
Final Report Published | 07/08/2009 | Must be published within 20 B-Days after the end of the second submission period |
Rule Commencement | 17/08/2009 |
Submissions received during the first submission period
Notice under Clause 2.5.12
22 May 2009
In accordance with clause 2.5.10 of the Market Rules, the IMO has extended the timeframe for preparing the Draft Rule Change Report for the Rule Change Proposal titled "Confidentiality of Accepted Outages" (Ref: RC_2009_05). The end date for preparing the Draft Rule Change Report is extended until Friday 19 June 2009. As a consequence of this extension, the remaining timelines for processing the proposal have been adjusted as follows:
- Second Submission Period 22 June - 17July 2009
- Final Report Published 07 August 2009
Reason for the extension
The period for preparing the Draft Rule Change Report needs to be extended to allow the IMO sufficient time to complete its analysis of the proposal.
Views from Rule Participants consulted on the extension
When deciding to extend the submission period, the IMO consulted with System Management (the proposer). System Management did not express any objections to the IMO regarding the proposed extension of the timeframe for preparing the Draft Rule Change Report.
Proposed Work Programme
- IMO undertake analysis of the proposal.
- IMO prepare and publish the Draft Rule Change Report.
- Interested parties make submissions on the Draft Rule Change Report during the second public submission period.
- IMO present the outcomes and its decision in the Final Rule Change Report.