Type: Standard Rule Change Process
Submitter: System Management
Title: Provision of Intermittent Generator Forecast Information
Market Rules Affected: Clause 7.2.5
Date Submitted: 16 February 2009
Date First Published on the IMO Website: 18 February 2009
Current Status: The Amending Rules commenced at 8:00am 1 July 2009
Event | Date | Comments |
---|---|---|
Notification Published | 18/02/2009 | |
First Submission period | 18/02/2009 – 1/04/2009 | The submission period is 6 weeks from the date the IMO published the notification |
Draft Report published | 22/04/2009 | Must be published within 20 B-Days after the end of the submission period |
Second submission period | 23/04/2009 – 21/05/2009 | The submission period is 20 B-Days from the date the IMO published the Draft Report |
Final Report Published | 19/06/2009 | Must be published within 20 B-Days after the end of the second submission period |
Rule Commencement | 01/07/2009 |