Rule Change: RC_2008_32

A Rule Change Proposal made by the Independent Market Operator on 2 October 2008
Last updated:

Type: Standard Rule Change Process

Submitter: IMO

Title: Calculation of IRCR

Market Rules Affected: Clause 8.6.1 and Appendix 5

Date Submitted: 02 October 2008

Date First Published on the IMO Website: 07 November 2008

Current Status: The Amending Rules commenced at 8:00am 1 May 2009

Event Date Comments
Notification Published 7/11/2008  
First Submission period 10/11/2008 – 22/12/2008 The submission period is 6 weeks from the date the IMO published the notification
Draft Report published 16/01/2009 Must be published within 20 B-Days after the end of the submission period
Second submission period 19/01/2009 – 16/02/2009 The submission period is 20 B-Days from the date the IMO published the Draft Report
Final Report Published 20/03/2009 Must be published within 20 B-Days after the end of the second submission period
Rule Commencement 1/05/2009  

 