Type: Standard Rule Change Process
Submitter: Synergy
Title: Capacity credits for solar facilities
Market Rules Affected: Clauses 4.11.2, 4.11.3, 4.11.3A and 4.11.3B.
Date Submitted: 15 December 2008
Date First Published on the IMO Website: 18 December 2008
Current Status: Closed.
Event | Date | Comments |
---|---|---|
Notification Published | 18/12/2008 | |
First Submission Period | 18/12/2008 – 5/02/2009 | The submission period is 6 weeks from the date the IMO published the notification |
Draft Report Published | 20/02/2009 | Must be published within 20 B-Days after the end of the submission period |
Second Submission Published | 23/02/2009 –24/04/2009 | This period has been extended in accordance with the notice of extension published on 12 March 2009 |
Final Report Published | 22/05/2009 | Must be published within 20 B-Days after the end of the second submission period |
Commencement | Not applicable | The Rule Change Proposal was rejected by the IMO |