Rule Change: RC_2008_29

A Rule Change Proposal made by the Independent Market Operator on 11 September 2008
Last updated:

Type: Standard Rule Change Process

Submitter: IMO

Title: Change to Curtailable Load de-registration timeframe

Market Rules Affected: 2.33.4(d)

Date Submitted: 11 September 2008

Date First Published on the IMO Website: 12 September 2008

Date Final Report Published: 16 January 2009

Current Status: Amending Rules commenced at 8:00am on 1 February 2009

Event Date Comments
Notification Published 12/09/2008  
First Submission period 15/09/2008 – 27/10/2008 The submission period is 6 weeks from the date the IMO published the notification
Draft Report published 21/11/2008 Must be published within 20 B-Days after the end of the submission period
Second submission period 24/11/2008 – 19/12/2008 The submission period is 20 B-Days from the date the IMO published the Draft Report
Final Report Published 16/01/2009 Must be published within 20 B-Days after the end of the second submission period
Rule Commencement 01/02/2009  

 