Rule Change: RC_2008_20

A Rule Change Proposal made by the Independent Market Operator on 17 July 2008
Last updated:

Type: Standard Rule Change Process

Submitter: IMO

Title: Demand Side Management – Operational Issues

Market Rules Affected: 2.29.5, 2.29.8A, 2.29.8B, 2.29.9A, 2.29.9B, 2.29.9C, 4.8.3, 4.10.1, 4.11.1, 4.11.4, 4.11.4A, 4.12.8, 4.14.1, 4.25.1, 4.25.2, 4.25.3B, 4.25.4, 4.25.4E, 4.25.4F, 4.25.9, 4.25A.1, 4.25A.2, 4.25A.3, 4.25A.4, 4.25A.5, 4.26.1, 4.26.1C, 4.26.2, 4.26.2C, 4.26.2D

Date Submitted: 17 July 2008

Date First Published on the IMO Website: 18 July 2008

Date Final Report Published: 24 November 2008

Current Status: The final set of Amending Rules commenced at 8.00am on 1 October 2011. The commencement table below shows the commencement date of each Amending Rule

Event Date Comments
Notification Published 18/07/2008  
First Submission period 18/07/2008 – 29/08/2008 The submission period is 6 weeks from the date the IMO published the notification
Draft Report published 26/09/2008 Must be published within 20 B-Days after the end of the submission period
Second submission period 27/09/2008 – 27/10/2008 The submission period is 20 B-Days from the date the IMO published the Draft Report
Final Report Published 24/11/2008 Must be published within 20 B-Days after the end of the second submission period
Rule Commencement 01/03/2009 (8:00am)
01/10/2009 (8:00am)
01/10/2010 (8:00am)
01/10/2011 (8:00am)
 

 

Submissions received during the second submission period

Amending Rules Commencement Dates

Rule NumberSubjectCommencement DateCommencement Notice
2.29.5Include new clause 2.28.8A1 March 20091
2.29.8AInterval Meters required.1 March 20091
2.29.8BVerification Test required within 20 days of certification.1 October 20103
2.29.9AMinimum activation notice of 4 hours.1 March 20091
2.29.9BAbility to increase activation time up to 4 hours.1 March 20091
2.29.9CCan’t extend minimum activation time beyond 4 hours.1 March 20091
4.8.3Loads must have same availability as DSM program1 March 20091
4.10.1DSM to be available noon to 8 pm.1 March 20091
4.11.1Certification precision to be 0.001 MW1 March 20091
4.11.4DSM cannot be Availability Class 11 March 20091
4.11.4ACapacity of DSM to be determined by its Relevant Demand1 March 20091
4.12.8Obligation drops to zero after two days of dispatch at maximum1 March 20091
4.14.1Capacity precision to be 0.001 MW1 March 20091
4.25.1DSM verification only to apply to period between October and March1 October 20103
4.25.2DSM verification testing to require load reduction for one Trading Interval1 October 20103
4.25.3BActivation of DSM deemed to be a Reserve Capacity Test1 October 20103
4.25.4Reserve Capacity testing1 October 20103
4.25.4ECapacity Payments to be refunded if capacity credits surrendered to IMO1 March 20091
4.25.4FCapacity cannot offer supplementary reserve capacity in the year that capacity credits are surrendered1 March 20091
4.25.9System Management testing of Loads1 October 20103
4.25A.1Verification test1 October 20103
4.25A.2Verification test1 October 20103
4.25A.3Verification test1 October 20103
4.25A.4Verification test1 October 20103
4.25A.5Verification test1 October 20103
4.26.1Refunds1 October 20092
4.26.1CRefunds1 October 20092
4.26.2Refunds1 October 20092
4.26.2CDetermination of Relevant Demand1 March 20091
4.26.2DDetermination of capacity shortfall1 October 20092
4.26.2ECalculation of refund1 October 20092
4.26.3Calculation of refund1 October 20092
4.26.3ACalculation of refund1 October 20092
6.17.6Calculation of Dispatch Payment1 October 20114
7.7.5DRemove clause determining quantity1 October 20114
7.7.10Cancellation of dispatch instructions1 March 20091
7.13.1Additional data to be provided by System Management to be used in settlement1 March 20091

 