Type: Standard Rule Change Process
Submitter: IMO
Title: Delay of Resource Plan Submissions
Market Rules Affected: 6.5.1 (a) and 6.5A.1(a)
Date Submitted: 10 April 2008
Date First Published on the IMO Website: 11 April 2008
Date Final Report Published: 18 August 2008
Current Status: Closed. The Amending Rules resulting from this Rule Change commenced at 08.00am on 20 August 2008
Event | Date | Comments |
---|---|---|
Proposal Received by IMO | 10/04/2008 | |
Notification Published | 11/04/2008 | |
First Submission period | 11/04/2008 – 23/05/2008 | The submission period is 6 weeks from the date the IMO published the notification |
Draft Report published | 23/06/2008 | Must be published within 20 B-Days after the end of the submission period |
Second submission period | 24/06/2008 – 21/07/2008 | The submission period is 20 B-Days from the date the IMO published the Draft Report |
Final Report Published | 18/08/2008 | Must be published within 20 B-Days after the end of the second submission period |
Rule Commencement | 20/08/2008 |