Type: Fast Track Rule Change Process
Submitter: Griffin Energy
Title: NTDL new and Overnight Loads
Market Rules Affected: 4.28.9 and Appendix 5 (amended). Appendix 5A (new)
Date Submitted: 20 February 2008
Date First Published on the IMO Website: 29 February 2008
Date Final Report Published: 02 April 2008
Current Status: Closed. The Amending Rules commenced at 08.00am on 1 May 2008
Event | Date | Comments |
---|---|---|
Proposal Received by IMO | 20/02/2008 | |
Notification Published | 29/02/2008 | |
Requests to be Consulted | 10/03/2008 | The last date a Rule Participant can contact the IMO requesting to be consulted on the change. |
Consultation Period | 04/03/2008 – 26/03/2008 | Must be completed within 15 B-Days from the date the notification is published |
Final Report Published | 02/04/2008 | Must be published within 20 B-Days from the date the notification is published |
Rule Commencement | 01/05/2008 |