Type: Standard Rule Change Process
Submitter: TransAlta
Title: Reduction of Capacity Credits
Market Rules Affected: 4.25.4A, 4.25.4B, 4.25.4C and 4.25.4D (all new)
Date Submitted: 15 February 2008
Date First Published on the IMO Website: 26 February 2008
Date Final Report Published: 03 July 2008
Current Status: Closed. The Amending Rules made from this Rule Change commenced at 08.00 am on 10 July 2008
Event | Date | Comments |
---|---|---|
Notification Published | 26/02/2008 | |
First Submission period | 26/02/2008 – 08/04/2008 | The submission period is 6 weeks from the date the IMO published the notification |
Draft Report published | 07/05/2008 | Must be published within 20 B-Days after the end of the submission period |
Second submission period | 08/05/2008 – 05/06/2008 | The submission period is 20 B-Days from the date the IMO published the Draft Report |
Final Report Published | 03/07/2008 | Must be published within 20 B-Days after the end of the second submission period |
Rule Commencement | 10/07/2008 |