Type: Standard Rule Change Process
Submitter: IMO
Title: SWIS Reliability Planning Criteria
Market Rules Affected: 4.5.9
Date Submitted: 27 November 2007
Date First Published on the IMO Website: 28 November 2007
Date Final Report Published: 09 April 2008
Current Status: Closed. The Amending Rules commenced on 10 April 2008
Event | Date | Comments |
---|---|---|
Proposal Received by IMO | 27/11/2007 | |
Notification Published | 28/11/2007 | |
First Submission period | 28/11/2007 – 10/01/2008 | The submission period is 6 weeks from the date the IMO published the notification |
Draft Report published | 08/02/2008 | Must be published within 20 B-Days after the end of the submission period |
Second submission period | 08/02/2008 – 10/03/2008 | The submission period is 20 B-Days from the date the IMO published the Draft Report |
Final Report Published | 09/04/2008 | Must be published within 20 B-Days after the end of the second submission period |
Rule Commencement | 10/04/2008 |