Submitter: System Management
Title: Treatment of DSM in outage planning and PASA
Market Rules Affected: 3.16, 3.17, 3.18 and 3.19
Date Submitted: 03 May 2007
Date First Published on the IMO Website: 11 May 2007
Date Final Report Published: 14 September 2007
Current Status: Closed. The amendments to Chapter 6 and 7 commenced on 1 October 2007
Event | Date | Comments |
---|---|---|
Proposal Received by IMO | 03-05-2007 | |
Notification Published | 11-05-2007 | |
Submission period | 11-05-2007 – 22-06-2007 | The submission period is 6 weeks from the date the IMO published the notification |
Draft Report published | 20-07-2007 | Must be published within 20 B-Days after the end of the submission period |
Second submission period | 20-07-2007 – 17-08-2007 | The submission period is 20 B-Days from the date the IMO published the Draft Report |
Final Report Published | 14-09-2007 | |
Rule Commencement | 01-10-2007 |