Type: Standard Rule Change Process
Submitter: Pilbara ISOCo
Title: Pilbara ISOCo Subchapter 10.1 Functions
Pilbara Networks Rules affected: Subchapter 10.1, Rule 279 and Rule 286
Date Submitted: 01 February 2025
Current Status: The Draft Rule Change Report has been published. The Second Submission Period is open until 19 May 2025.
Event | Date | Comments |
---|---|---|
Notification Published | 04/02/2025 | |
First Submission Period | 04/02/2025 - 19/03/2025 | The end of the submission period is at least 30 Business Days from the publication of the Rule Change Notice. |
Draft Rule Change Report Published | 16/04/2025 | The Draft Rule Change Report must be published within 20 Business Days from the end of the first submission period. |
Second Submission Period | 16/04/2025 - 19/05/2025 | The end of the submission period is at least 20 Business Days from the publication of the Draft Report. |
Final Rule Change Report Published | 17/06/2025 | The Final Rule Change report must be published within 20 Business Days after the end of the second submission period. |
Commencement | 18/06/2025 |