Muja C Unit 6 in reserve mode and online for summer 2024-25

Unit 6 at Muja C Power Station will be made available during the 2024-25 high demand period to ensure wider energy system security during the hot summer months, in line with updated forecasts by the independent Australian Energy Market Operator (AEMO).
  • Muja C Unit 6 retirement to be pushed back six months to April 2025
  • Reserve outage mode will support electricity stability over the summer period
  • Operational decision in line with latest independent energy forecasts to further mitigate electricity supply risks and has minimal impact to workforce
  • No impact to WA Government's phased transition to cleaner, reliable and affordable energy

Unit 6 at Muja C Power Station will be made available during the 2024-25 high demand period to ensure wider energy system security during the hot summer months, in line with updated forecasts by the independent Australian Energy Market Operator (AEMO).    

Synergy's Unit 6 in Collie will be placed on reserve outage mode from 1 October 2024 until 1 April 2025.

During reserve outage mode, AEMO will be able to request, with three days' notice, that Unit 6 be made available for significant peak demand events.

This will not impact the planned retirement of the State's remaining coal-fired units by 2030, with Collie and Muja Power Stations scheduled to close in 2027 and 2029 respectively.

Muja C Unit 6 was previously scheduled to be retired in October 2024, as part of the WA Government's phased transition to retire all State coal-fired power stations by 2030 and meet its net zero emissions target by 2050.

Comments attributed to Energy Minister Bill Johnston:

"The Cook Government is adapting to the changing energy landscape to ensure a secure energy supply for residents.

"Putting Unit 6 at Muja in reserve outage mode will allow us to call on the unit, if needed, during periods of high demand.

"Western Australia has the most remote stand-alone energy system in the world and the supply of reliable electricity to residents is the highest priority.

"This will have minimal impact on Synergy staff and contractors working at Muja Power Station, where around five staff will be affected