From 11 April 2019 to 02 December 2024, we have received 89 unsolicited MLPs. The table below outlines the number of proposals received in each industry category.
Category | Number received |
---|---|
Property | 22 |
Health | 14 |
Community services | 11 |
Infrastructure | 22 |
Tourism | 3 |
Telecommunications and ICT | 4 |
Education | 2 |
Publishing and media | 1 |
Retail | 2 |
Environmental | 2 |
Agriculture and farming | 1 |
Mining and resources | 2 |
Transport | 1 |
Other | 2 |
Total | 89 |
Of those 89 proposals:
- 5 have been completed
- 11 are current
- 6 were withdrawn
- 11 were referred
- 56 were declined.
The table below outlines the primary reason why 73 MLPs did not progress as they were either declined, referred or withdrawn. (Some may not have progressed for multiple reasons).
Reasons | Number of proposals |
---|---|
Scope and Priorities Assessment | 34 |
Procurement Pathway Assessment | 8 |
Evaluation Criteria Assessment | 25 |
Withdrawn by Proponent | 6 |
Total | 73 |
Completed proposals
Visit the Completed Market-led Proposals webpage for more details.
Proposals in Stage 2
Show moreMLP24006 Busselton Mental Health Care Hospital
- Status: Invited to Stage 2 of the MLP Process, with the ability to negotiate on an exclusive basis
- Proponent: Sophron Healthcare Pty Ltd
- Industry: Mental Health
- Governance for Stage 2: Centrally governed process with the Mental Health Commission as lead agency
- Description: Sophron Healthcare is proposing to fund the construction of a public-private mental health care hospital on privately-owned land in Busselton, in the southwest of Western Australia. The proponent is seeking a commitment from WA Government for the provision of public mental health services within the new hospital, for a five-year service period.
- Current status: Stage 1 evaluation is complete. Cabinet has approved the proponent entering detailed negotiations with the State, led by the Mental Health Commission. Sophron Healthcare has now been invited to complete a full business case.
- Next advice: Update will be provided at the conclusion of Stage 2.
MLP22008 Jetty C, Albany
- Status: Invited to Stage 2 of the MLP Process, with the ability to negotiate on an exclusive basis
- Proponent: Harvest Road Oceans Pty Ltd
- Industry: Infrastructure
- Governance for Stage 2: Centrally-led by the Department of Transport
- Description: The proposal seeks to acquire Jetty C to enable permanent berthing of the Proponent’s current and planned expanded fleet of vessels adjacent to its onshore processing facility, to support increased shellfish production.
- Current status: Proposal has a reasonable prospect of meeting all the criteria of the MLP Policy and has been invited to complete a full business case with the Department of Transport
- Next advice: Update will be provided at the conclusion of Stage 2
MLP19026 Palliative Care Hub Osborne Park
- Status: Invited to Stage 2 of the MLP process, with the proponent to receive a First Mover Advantage in an open and transparent process.
- Proponent: Bethesda Health Care and The Bethanie Group Incorporated.
- Industry: Health.
- Governance for Stage 2: Agency-led process via the Department of Health.
- Description: Proposing the construction and operation of a facility integrating a 120-bed residential aged care and dementia care facility, and a 25-bed specialist inpatient palliative care hub.
- Current status: Proposal has a reasonable prospect of meeting all the criteria of the MLP Policy, however, did not justify the right for exclusive negotiation. The Department of Health released an Expression of Interest that closed on 9 November 2021. The proponent was assigned a 20 per cent bid premium applied to their overall score, in an open and transparent process. A consortium of Bethesda Health Care and The Bethanie Group was the successful respondent and has been invited to submit a business case to the Department of Health.
- Next advice: Update will be provided upon advice from the Department of Health in relation to outcomes of the business case evaluation in Stage 2.
MLP20002 Swanbourne Village Project
- Status: Invited to Stage 2 of the MLP process, with the proponent to receive a First Mover Advantage in an open and transparent Expression of Interest process.
- Proponent: Cedar Woods Properties Limited (Cedar Woods).
- Industry: Property Development and Construction.
- Governance for Stage 2: Centrally-led process via the Department of Planning, Lands and Heritage.
- Description: Cedar Woods proposed the development of State-owned land within the Railway Reserve adjacent to Swanbourne Station to enhance the performance of the station, provide a better context for the proposed Congdon Street Bridge replacement and deliver METRONET objectives. The development would be planned to include a mix of residential, retail, commercial and community uses, and designed to respond to the local Swanbourne Village context.
- Current status: The proposal was determined to have a reasonable prospect of meeting the criteria of the MLP Policy however did not justify the right for exclusive negotiation. The State Government has undertaken baseline due diligence to identify land within the Railway Reserve that is suitable for urban development. The baseline due diligence will be provided to respondents to the Invitation for Expressions of Interest.
- An Invitation for Expression of Interest has been released to the market via Tenders WA inviting proponents to express their interest in the Swanbourne development opportunity. The Proponent will receive a 15 per cent bid premium to its score against the Value for Money criterion in the evaluation of submissions. The Invitation for Expression of Interest closed on 19 January 2024 and submissions are now under evaluation.
- Next advice: Update will be provided at the conclusion of the Expression of Interest process.
MLP20003 Graylands Hospital Site and Shenton Precinct
- Status: Invited to Stage 2 of the MLP process, with the ability to negotiate on an exclusive basis.
- Proponent: Hesperia Property Pty Ltd.
- Industry: Property Development and Construction.
- Governance for Stage 2: Centrally-led process via the Department of Planning, Lands and Heritage.
- Description: Proposing the development of land to create an urban infill project. The proposal incorporates the implementation of an odour management and solar power solution at the Subiaco Waste Water Treatment Plant (WWTP). The proposal is investigating the potential to repurpose the current Graylands Hospital Site for future urban development.
- Current status: This concept has a reasonable prospect of meeting the criteria of the MLP Policy and the proponent has been invited to complete a full business case with the Department of Planning, Lands and Heritage, in consultation with other impacted agencies as required.
- To note: that all planning, feasibility and due diligence must first consider the current use of the Graylands Hospital site in determining any potential future use of the current Graylands Hospital Site. This will be completed in collaboration with the Department of Health and the Graylands Reconfiguration and Forensic Taskforce. Please see media release relating to the Graylands Taskforce.
- To note: that there is no endorsed nor funded disinvestment and reconfiguration of Graylands Hospital site and its services at this stage. Any future changes to the WWTP will be in consultation with the Water Corporation.
- Next advice: Update will be provided at the conclusion of Stage 2.
MLP20005 Land Exchange Byford and Ellenbrook
- Status: Invited to Stage 2 of the MLP process, with the ability to negotiate on an exclusive basis.
- Proponent: LWP Group Pty Ltd.
- Industry: Land and Property Development.
- Governance for Stage 2: Centrally led by the Department of Planning, Lands and Heritage.
- Description: Proposal is an exchange of State urban zoned land in Henley Brook with land owned by the Proponent in Byford and Ellenbrook Town Centres to enhance the State’s development options at the two METRONET precincts.
- Current status: Proposal has a reasonable prospect of meeting all the criteria of the MLP Policy and is now under evaluation and subject to negotiation in Stage 2.
- Next advice: Update will be provided at the conclusion of Stage 2.
Declined, referred or withdrawn proposals
Show moreMLP21011 Collie to Coast
- Proponent: South West Irrigation Management Cooperative Limited, and South West Irrigation Asset Cooperative Limited.
- Industry: Water distribution, Irrigation.
- Lead Agency: Centrally led by the Department of Primary Industries and Regional Development (DPIRD).
- Description: Proposal to deliver a water infrastructure project designed to improve water availability and quality, for the benefit of agriculture and industrial water users in the South-West Region.
- Previous status: The proposal was invited to Stage 2 of the MLP process, with the ability to negotiate on an exclusive basis.
- Current status: The proposal has been referred outside of the MLP process, for further progression and negotiation between DPIRD and the proponent. The MLP process is closed.
MLP19008 Second Home Innovation Hub at Ainslie House
- Status: Invited to Stage 2 of the MLP process, with the ability to negotiate on an exclusive basis.
- Proponent: Hesperia Property Pty Ltd and Second Home (the Consortium)
- Industry: Property and innovation.
- Governance for Stage 2: Centrally-led by the Department of Planning, Lands and Heritage.
- Description: The proposal seeks to establish a Second Home Innovation Hub at Ainslie House.
- Previous status: Proposal has a reasonable prospect of meeting all the criteria of the MLP Policy and has been invited to complete a full business case with the Department of Planning, Lands and Heritage.
- Current status: Proponent withdrew from the MLP process; the process is closed.
MLP19027 Bullsbrook Intermodal Container Terminal
- Proponent: Harvis Capital Pty Ltd.
- Industry: Land Development and Primary Production.
- Lead Agency: Centrally-led process via the Department of Transport.
- Description: The proposal sought investment in rail to deliver a long-term integrated solution to Perth’s future infrastructure needs, by facilitating an intermodal container terminal at Bullsbrook.
- Previous Status: Invited to Stage 2 of the MLP process, with the ability to negotiate on an exclusive basis.
- Current status: Proposal did not progress to Stage 3; the process is closed.
MLP20019 Integrated Finfish Aquaculture Precinct
- Proponent: Harvest Road Oceans Pty Ltd
- Industry: Aquaculture
- Lead Agency: Centrally-led process via Department of Primary Industries and Regional Development
- Description: Proposed development of a land-based yellowtail kingfish aquaculture precinct. The proponent would construct and operate a grow-out facility supplied by a hatchery constructed and operated by the State, with infrastructure shared by the parties. The proposal incorporated capacity for other commercial grow-out operators in the precinct.
- Previous status: The Proposal had a reasonable prospect of meeting all the criteria of the MLP Policy, however did not justify the right for exclusive negotiation. The State issued an Invitation for Expression of Interest on Tenders WA for this or similar proposal, in an open and transparent process. In accordance with the First Mover Advantage of the MLP Policy, the proponent received a 20 per cent bid premium applied to their total score as part of the evaluation.
- Current Status: Proposal did not progress to Stage 2 Business Case; the MLP process is closed.
MLP20021 Mid-West Desalination Project
- Proponent: AGI Operations Pty Ltd
- Industry: Land Development and Primary Production.
- Lead Agency: Centrally-led process via the Department of Jobs, Tourism, Science and Innovation.
- Description: Proposal is for the proponent to fund the construction of a reverse osmosis desalination plant at Oakajee Strategic Industrial Area (OSIA) to supply scheme water to Water Corporation for the Geraldton region. Proponent proposes to supply water to industrial, mining and agricultural customers.
- Previous Status: Invited to Stage 2 of the MLP process, with the proponent to receive a First Mover Advantage in an open and transparent process.
- Current status: Proponent withdrew from the MLP process; the process is closed.